Question: Table A we Activity Predecessor Time(weeks) 8 B A 6 4 D 9 E A 11 F B 3 D, E, F 1 Using Table

Table A we Activity Predecessor Time(weeks) 8 B A
Table A we Activity Predecessor Time(weeks) 8 B A 6 4 D 9 E A 11 F B 3 D, E, F 1 Using Table A, what is the earliest completion time for this project? Multiple Choice 18 weeks 19 weeks 20 weeks