Question: Table A Activity Predecessor Time(weeks) A 8 B A 6 4 D 9 E A 11 F B 3 G D, E, F Using Table

Table A Activity Predecessor Time(weeks) A 8 B A

Table A Activity Predecessor Time(weeks) A 8 B A 6 4 D 9 E A 11 F B 3 G D, E, F Using Table A, what is the earliest completion time for this project? 1 18 weeks 19 weeks 20 weeks 0 21 weeks