Question: table [ [ Activity , Expected Time ( weeks ) , Immediate Predecessor ( s ) ] , [ A , 5 , -

\table[[Activity,Expected Time (weeks),Immediate Predecessor(s)],[A,5,--],[B,3,-],[C,2,A],[D,5,B],[E,4,C, D],[F,7,D]]
a. Choose the correct network diagram for this project.
A.
c.
D.
Q
b. Identify the critical path and estimate the project's duration.
The critical path is path and the project duration is weeks. (Enter your response as an integer.)