Question: table [ [ Activity Normal _ timeCrash _ timeNormal _ costCrash _ costSlack ] , [ A , 3 1 , 2 1 ,
tableActivity NormaltimeCrashtimeNormalcostCrashcostSlackABCDEF
The table shows normal time in days crash time in days normal cost in dollars crash cost in dollars and slack time in days of activities in a small construction project. According to this table which activity must be crashed first? Assume there is only one critical path. Only type the name of the activity, Example: A @orsdemir. Copyrighted content. Cannot be posted.