Question: Table EX 13.9 displays the optimistic, most likely, and pessimistic activity durations for the transition to paperless project in EX 13.8. Table EX 13.9 Activity
Table EX 13.9 displays the optimistic, most likely, and pessimistic activity durations for the transition to paperless project in EX 13.8. Table EX 13.9 Activity Optimistic Most Likely Pessimistic A 3 4 2 B 2 3 1 C 6 7 5 D 2 3 1 E 15 16 17 F 4 5 3 a. Calculate the mean duration for each activity. b. Calculate the variance of each activity time. c. Identify the mean and standard deviation for each path. d. Calculate project completion probability for nineteen, twenty, and twenty-one weeks