Question: table [ [ ACTIVITY , PREDECESSOR ( S ) , OPTIMISTIC,MOST LIKELY,PESSIMISTIC ] , [ A , - , 4 , 8 , 1
tableACTIVITYPREDECESSORSOPTIMISTIC,MOST LIKELY,PESSIMISTICABACADAEBFE CGE CHFIFJD G HKI, J
a What is the expected estimated time for activity C
b What is the variance for activity C
c Based on the calculation of estimated times, what is the critical path?
d What is the estimated time of the critical path?
e What is the activity variance along the critical path?
f What is the probability of completion of the project before week