Question: table [ [ Activity , Predecessor ( s ) , Duration ( days ) ] , [ A , - , 5 ] ,

\table[[Activity,Predecessor(s),Duration (days)],[A,-,5],[B,A,20],[C,A,15],[D,A,5],[E,B, C,60],[F,D,15],[G,E,20],[H,E,15],[I,F, G, H,2]]
Figure 7-6 Network Scheduling Data
Consider the network scheduling data presented in Figure 7-6. How many days of slack are associated with activity F?
 \table[[Activity,Predecessor(s),Duration (days)],[A,-,5],[B,A,20],[C,A,15],[D,A,5],[E,B, C,60],[F,D,15],[G,E,20],[H,E,15],[I,F, G, H,2]] Figure 7-6 Network Scheduling Data Consider