Question: table [ [ Activity , Predecessor, table [ [ Duration ] , [ ( Months ) ] ] , table [ [
tableActivityPredecessor,tableDurationMonthstableCost perActivity RandsARBRCStart days after finish of ARDA; BREBRFD; ER
tableGCRHGRIFRJER
Overhead OH cost for the project amounts to R per month.
Draw the precedence diagram from A to J
a Determine the critical path
b determine the duration or the project, overhead cost, sum of the activity cost and the total cost of the project
c Calculate the total float and free float for each of the activities in the precedence diagram
Please explain each step like you explaining it to a year old