Question: table [ [ Activity , Predecessor, table [ [ Duration ] , [ ( Months ) ] ] , table [ [

\table[[Activity,Predecessor,\table[[Duration],[(Months)]],\table[[Cost per],[Activity (Rands)]]],[A,-,1,R20000],[B,-,2,R80000],[C,Start 2 days after finish of A,3,R30000],[D,A; B,1,R15000],[E,B,6,R140000],[F,D; E,3,R60000]]
\table[[G,C,4,R90000],[H,G,10,R120000],[I,F,3,R30000],[J,E,4,R30000]]
Overhead (O.H.) cost for the project amounts to R10000 per month.
Draw the precedence diagram from A to J
a. Determine the critical path
b. determine the duration or the project, overhead cost, sum of the activity cost and the total cost of the project
c. Calculate the total float and free float for each of the activities in the precedence diagram
Please explain each step like you explaining it to a 5 year old
 \table[[Activity,Predecessor,\table[[Duration],[(Months)]],\table[[Cost per],[Activity (Rands)]]],[A,-,1,R20000],[B,-,2,R80000],[C,Start 2 days after finish of A,3,R30000],[D,A; B,1,R15000],[E,B,6,R140000],[F,D; E,3,R60000]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!