Question: table [ [ Activity , Predecessor, table [ [ Duration ] , [ ( Months ) ] ] , table [ [
tableActivityPredecessor,tableDurationMonthstableCost perActivity RandsARB
Draw the precedence diagram
aDetermine the critical path
b The duration of the project, overhead cost, the sum of the activity cost and the total cost of the project
c calculate the Total float and Free float for each of the activities in the precedence diagram