Question: table [ [ activity predecessors ] , [ A , , 5 , 4 , 4 5 0 0 , 8 0 0 0

\table[[activity predecessors],[A,,5,4,4500,8000],[A,A,4,3,3500,6000],[B,B,5,5,2000,2000],[C,C,3,1,3000,11000],[D,B,7,4,4500,7500],[E,B,6,6,5500,5500]]
The table shows normal time, crash time, normal cost, crash cost of activities in a project. According to this table which activity must be crashed first? (Only enter the name of
 \table[[activity predecessors],[A,,5,4,4500,8000],[A,A,4,3,3500,6000],[B,B,5,5,2000,2000],[C,C,3,1,3000,11000],[D,B,7,4,4500,7500],[E,B,6,6,5500,5500]] The table shows normal time, crash time, normal cost,