Question: Consider the following table, Activity Predecessor(s) Duration J -- 4 K -- 7 L J 7 M J,K 3 N L, M 6 O K,
Consider the following table, Activity Predecessor(s) Duration J -- 4 K -- 7 L J 7 M J,K 3 N L, M 6 O K, N 5 a) Draw the Network diagram b) Calculate the critical path and expected duration
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts