Question: table [ [ Activity , table [ [ Predecesso ] , [ r ] ] , Time ( days ) ] , [

\table[[Activity,\table[[Predecesso],[r]],Time (days)],[A,--,8],[B,--,6],[C,--,3],[D,A,B,10],[E,C,8],[F,A,5],[G,D,E,3],[H,G,4]]
Using Table 7.5, what is the earliest that activity D can be finished?
Select one:
A.8 days
B.25 days
C.13 days
D.18 days
 \table[[Activity,\table[[Predecesso],[r]],Time (days)],[A,--,8],[B,--,6],[C,--,3],[D,A,B,10],[E,C,8],[F,A,5],[G,D,E,3],[H,G,4]] Using Table 7.5, what is the earliest that activity