Question: table [ [ Activity , table [ [ Immediate ] , [ Predecessor ( s ) ] ] , Duration ( days )

\table[[Activity,\table[[Immediate],[Predecessor(s)]],Duration (days)],[A,----,5],[B,A,2],[C,A,4],[D,C,B,1],[E,C,B,6],[F,B,2],[G,D,E,3],[H,F,G,4]]
Based on the above table, draw an AOA network.
List ALL paths and identify the critical path(s).
You could draw the network on a piece of paper or use Excel, Word, or the online tools in lucidchart. If on a piece of paper, you should take a picture of the completed network and submit the picture file on D2L. Please draw the AOA network
 \table[[Activity,\table[[Immediate],[Predecessor(s)]],Duration (days)],[A,----,5],[B,A,2],[C,A,4],[D,C,B,1],[E,C,B,6],[F,B,2],[G,D,E,3],[H,F,G,4]] Based on the above table, draw an AOA network.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!