Question: Table below is a time-phased net requirements for Widgets over the next six weeks. The setup cost is $200 and the holding cost is $0.30

Table below is a time-phased net requirements for
Table below is a time-phased net requirements for
Table below is a time-phased net requirements for Widgets over the next six weeks. The setup cost is $200 and the holding cost is $0.30 per unit per week. Using the least unit cost heuristics, indicate the number of units to produce for each of the following period. Enter your answer as integer. The total holding and setup cost for the least cost unit lot sizing method is $