Question: Table below shows a 9-month project. We are checking the status (schedule & budget) of this project at the end of the 6th month:
Table below shows a 9-month project. We are checking the status (schedule & budget) of this project at the end of the 6th month: Earned Value Table for a Project Activity Staffing Blueprinting Prototype Dev. Full Design Construction Transfer Punch List Monthly Plan Cumulative Monthly Actual Cumulative Actual Jan Feb March Apr May June July August Sep Plan % Compl Value 5 10 5 100% 10 5 5 5 5 5 10 20 10 15 10 15 15 15 10 10 10 15 15 15 6 24 16 32 40 44 000 80% 70% 40% 40% 40% 0% 1) Complete the earned value table 2) Calculate EV, PV, AC, Project Schedule Variance, Project Cost Variance, Project Schedule Performance Index, Project Cost Performance Index, Original Project Completion Time, Original Project Budget, Expected Project Completion Time (based on the trend), and Expected Project Total Cost (based on the trend). 3) Comment on the budget and schedule status of this project.
Step by Step Solution
3.31 Rating (151 Votes )
There are 3 Steps involved in it
Complete the earned table The earned value table is used to calculate the earned value of a project ... View full answer
Get step-by-step solutions from verified subject matter experts
