Question: table [ [ Key Terms, M a t c h 1 = , Definition ] , [ 1 , Project Network,A , table

\table[[Key Terms,Match1=,Definition],[1,Project Network,A,\table[[An activity that has more than one activity immediately],[preceding it (more than one dependency arrow flowing to],[it).]]],[2,Activity,2=,B,The path with the longest duration through the network.],[3,Burst Activity,3=,C,The attempt by a planner to return to an earlier activity],[4,Merge Activity,4=,D,\table[[This pass starts with the last project activity(ies) on the],[network, and traces backwards on each path, subtracting],[activity times to find the late start (LS) and Late finish (LF)],[times for each activity. -> Latest Time]]],[5,Path,5=,E,\table[[The amount of time an activity can be delayed without],[delaying any immediately following (successor) activity.],[Note: This number can never be negative]]],[6,Critical Path,6=,F,\table[[An element of the project that requires time but may not],[require resources. It may be made up of one or more work],[packages (WPs).]]],[7,Forward Pass,7=,G,\table[[The minimum amount of time a dependent activity must],[be delayed to begin or end.]]],[8,Forward Pass Computation =,8=,H,LF- Duration = LS],[9,Backward Pass,9=,1,\table[[Tells us the amount of time an activity can be delayed and],[not delay the project.]]],[10,Backward Pass Computation =,10=,J,\table[[Reflects the likelihood the original critical path(s) will],[change once the project is initiated.]]],[11,Total Slack,11=,K,A sequence of connected dependent activities],[12,Free Slack,12=,L,\table[[A graphic flow chart depicting the project activities that],[must be completed, the logical sequences, the],[interdependencies of the activities to be completed, and],[the times for the activities to start and finish along with the],[longest path(s) through the network-the critical path.]]],[13,Network Sensitivity,13=,M,\table[[An activity that has more than one activity immediately],[following it (more that one dependency arrow flowing],[from it).]]],[14,Looping,14=,N,\table[[This pass starts with the first project activity(ies) and traces],[each path (chain of sequential activities) through the],[network to the last project activity(ies), Earliest Time]]],[15,Lag,15=,0,ES+ Duration =EF
 \table[[Key Terms,Match1=,Definition],[1,Project Network,A,\table[[An activity that has more than one activity immediately],[preceding

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!