Question: table [ [ , , table [ [ Duration Estimates ] , [ Most ] ] , , ] , [ Activity ,

\table[[,,\table[[Duration Estimates],[Most]],,],[Activity,Precedes,OptimisticLikelyPessimistic,,],[Start,U,V,-,-,-],[U,W,35,50,65],[V,W, X,28,40,52],[W,Z,26,35,44],[X,Y,28,40,52],[Y,Z,26,29,38],[Z,End,36,60,84]]
What is the probability that the critical path for this project will be completed within 200 days?
 \table[[,,\table[[Duration Estimates],[Most]],,],[Activity,Precedes,OptimisticLikelyPessimistic,,],[Start,U,V,-,-,-],[U,W,35,50,65],[V,W, X,28,40,52],[W,Z,26,35,44],[X,Y,28,40,52],[Y,Z,26,29,38],[Z,End,36,60,84]] What is the probability that the critical path