Question: Task 1 . Read the given scenario carefully and complete the table given. Scenario There was a multi stories apartment building project for which a

Task1. Read the given scenario carefully and complete the table given.
Scenario
There was a multi stories apartment building project for which a deep construction was
designed for a parking with 3-meter height below the ground level on a raft (Mat) foundation.
Then, a 3-meter excavation was needed to create the parking space, but it could not happen
without a proper retaining wall along the boundary, first. ABC geotechnical contractor was the
project consultant who did soil investigation and provided a geotechnical report in which the
soil properties was given. Accordingly, structural designer designed a continuous concrete wall
as the retaining wall system. This system was suitable only in a site with pure sand soil for
which a special plant and equipment were needed to excavate the site. The system included
a gap with 400 mm wide and 6 meters deep along the boundary that enable immediate
placing reinforcement and pouring prefabricated concrete transported to the site by concrete
mixer trucks. Pouring concrete was supposed to be followed by placing vertical 6-meters bars
in two layers every 300 mm. The site was identified as a different soil type that contains hard
limestone impeding the special plant operation when the construction started. It was about
winter with heavy rains that caused the client to worry about heavy rain to stop the project
progress. The sub-structure (below the ground level) was planned to be completed before
rainy season. The operation failed after two hours of the project commencement. A high
volume of concrete was ordered, and concrete trucks gotstuck and could not unload concrete
on site. There was a bad traffic outside the site. The trucks went back to destroy the concrete.
Also, there was an economic instability, fast and high inflation. Therefore, the client asked the
designer to rush to re-design after the initial design failed\table[[No,Risk type,Risk definition,\table[[Specify the risk and its],[category (Residual/],[secondary/ inherent) and],[occurred in the project],[described]],\table[[Mitigation],[action/s]]],[1,,,,],[2,,,,],[3,,,,],[4,,,,],[5,,,,],[6,,,,],[7,,,,],[8,,,,],[9,,,,],[10,,,,],[11,,,,]]
Task 1 . Read the given scenario carefully and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!