Question: TASK 5 EARNED VALUE ANALYSIS (6 MARKS) It was decided to budget the project using normal duration of each of the activities. The progress of

 TASK 5 EARNED VALUE ANALYSIS (6 MARKS) It was decided to

TASK 5 EARNED VALUE ANALYSIS (6 MARKS) It was decided to budget the project using normal duration of each of the activities. The progress of the project activities exactly at the middle of the planned project duration are given below: Activity Percent Completed Actual Cost to Date ($) A 100 200,000 100 330,000 100 600,000 200,000 400,000 60,000 130,000 SU BTASKS Based on the given status of the project determine the followings: A. Planned Value (PV) and Earned Value (EV) at the status date 1 B. Schedule Variance (SV) and Schedule Performance Index (SPI) at the status date 1 C. Cost Variance (CV) and Cost Performance Index (CPI) at the status date 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!