Question: task A (4 days) and task B (5 days) are linked by the finish to finish with a 3 day lag. A is the predecessor
task A (4 days) and task B (5 days) are linked by the finish to finish with a 3 day lag. A is the predecessor and B is the successor. how long does it take to complete both tasks?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock