Question: Task Budget (PV) 1 2 3 4 5 6 7 8 9 A 300 200 100 B 1000 300 200 200 300 C 600 200

Task Budget (PV) 1 2 3 4 5 6 7 8 9
A 300 200 100
B 1000 300 200 200 300
C 600 200 200 200
D 500 200 300
E 100 100
Period PV Total 200 100 200 500 400 200 300 200 400
Cumulative PV Total 200 300 500 1000 1400 1600 1900 2100 2500

Status at the end ofPeriod 4

Task % complete EV AC PV CV SV
A finished 250
B 50% 600
C 50% 400
D 0 0 0
E 0 0 0

Question 1

What is the earned value for the project this time?

Question 2

What is the project's current Schedule Variance?

Question 3

What is the SPI? (Show some intermediate steps of the calculation so I can assign partial credit)

Question 4

What is the CPI? (Show some intermediate steps of the calculation so I can assign partial credit)

Question 5

What is theCumulative CPI * SPI EAC? (Show some of your work so I can assign partial credit)

Question 6

What is the PCIB? (Show some intermediate steps of the calculation so I can assign partial credit)

Question 7

Based on your earned value analysis, describe the status of the project and what problems (if any) need to be addressed?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!