Question: Task Budget (PV) 1 2 3 4 5 6 7 8 9 A 300 200 100 B 1000 300 200 200 300 C 600 200
| Task | Budget (PV) | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 |
|---|---|---|---|---|---|---|---|---|---|---|
| A | 300 | 200 | 100 | |||||||
| B | 1000 | 300 | 200 | 200 | 300 | |||||
| C | 600 | 200 | 200 | 200 | ||||||
| D | 500 | 200 | 300 | |||||||
| E | 100 | 100 | ||||||||
| Period PV Total | 200 | 100 | 200 | 500 | 400 | 200 | 300 | 200 | 400 | |
| Cumulative PV Total | 200 | 300 | 500 | 1000 | 1400 | 1600 | 1900 | 2100 | 2500 |
Status at the end ofPeriod 4
| Task | % complete | EV | AC | PV | CV | SV |
|---|---|---|---|---|---|---|
| A | finished | 250 | ||||
| B | 50% | 600 | ||||
| C | 50% | 400 | ||||
| D | 0 | 0 | 0 | |||
| E | 0 | 0 | 0 |
Question 1
What is the earned value for the project this time?
Question 2
What is the project's current Schedule Variance?
Question 3
What is the SPI? (Show some intermediate steps of the calculation so I can assign partial credit)
Question 4
What is the CPI? (Show some intermediate steps of the calculation so I can assign partial credit)
Question 5
What is theCumulative CPI * SPI EAC? (Show some of your work so I can assign partial credit)
Question 6
What is the PCIB? (Show some intermediate steps of the calculation so I can assign partial credit)
Question 7
Based on your earned value analysis, describe the status of the project and what problems (if any) need to be addressed?