Question: Task C has two immediate predecessors, tasks A and B. Task A is planned to take 5 days to complete; Task B is planned to
Task C has two immediate predecessors, tasks A and B. Task A is planned to take 5 days to complete; Task B is planned to take 10 days. The early start time for both tasks is August 1. The actual start dates for tasks A and B are August 2 and August 1, respectively. At the end of August 4, Task A is assessed to be 20 percent completed and Task B, 30 percent completed. What is the expected early start time for Task C?