Question: Task C has two immediate predecessors, Tasks A and B. Task C also has two immediate followers, Tasks D and E. Task A has an

Task C has two immediate predecessors, Tasks A and B. Task C also has two immediate followers, Tasks D and E. Task A has an early finish time of 3 days, and Task B has an early finish time of 5 days. Task D has a late start time of 10 days and Task E has a late start time of 8 days. Task C is 2 days long. What is the late finish time of Task C? 5 days 2 days 6 days 8 days 7 days