Question: Task C is directly preceded by two tasks - task A and task B . Task A: Has an expected task completion time of five

Task C is directly preceded by two tasks-task A and task B. Task A: Has an expected task completion time of five weeks and an ES time of week 6. Task B: Has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The ES for activity C is week 1)7.2)14.3)12.4)24.