Question: 14. Task C is directly preceded by two taskstask A and task B. Task A has an expected task completion time of five weeks and
14. Task C is directly preceded by two taskstask A and task B. Task A has an expected task completion time of five weeks and an ES time of week 6. Task B has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The ES for activity C is week
A. 24 B. 14. C. 7. D. 12. E. 17