Question: Use the baseline plan presented here to complete the progress update provided at the end of the 6 th period, and then answer the questions
Use the baseline plan presented here to complete the progress update provided at the end of the 6th period, and then answer the questions that follow: (critical tasks are in red/bold fonts)
| Task | Budget | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| A | 2000 | 1000 | 1000 | |||||||||||
| B | 2400 | 1200 | 1200 | |||||||||||
| C | 3000 | 500 | 500 | 500 | 500 | 500 | 500 | |||||||
| D | 2500 | 500 | 500 | 500 | 500 | 500 | ||||||||
| E | 1600 | 400 | 400 | 400 | 400 | |||||||||
| F | 2000 | 500 | 500 | 500 | 500 | |||||||||
| G | 1000 | 500 | 500 | |||||||||||
| Cumulative |
Update at the end of 6th Period:
| Task | % Complete | EV | AC | PV | CV | SV | CPI | SPI |
|---|---|---|---|---|---|---|---|---|
| A | 100% | 1500 | ||||||
| B | 100% | 2000 | ||||||
| C | 80% | 2100 | ||||||
| D | 80% | 1800 | ||||||
| E | 50% | 600 | ||||||
| Cumulative Totals | 8000 |
- The budget at completion for this project is: (Just enter a number without "$" or ",":
- Based on the baseline plan, this project is expected to finish by period (Just enter a number without any units)
- The Earned value (EV) of task C at this point is is: (just entering a number without "$" or ","):
- The cumulative cost variance (CV) is: (just entering a number without "$" or ","):
- The cumulative SPI is: (Just enter a number with two digits after the decimal, for example: 1.56):
- Based on information you have thus far, it is reasonable to conclude that the project will be completed ___________ the date that was originally communicated as the its completion date.