Question: 1. With reference to your completed status report, the Cost Variance at the end of week 5 suggests that: Group of answer choices R1 600
1. With reference to your completed status report, the Cost Variance at the end of week 5 suggests that: Group of answer choices
R1 600 000 ahead of schedule
R1 600 000 under budget
R1 600 000 over budget
2. The Cost Performance index at the end of week 5 (rounded to two decimal points) indicates that:
For every R1 planned you have accomplished an extra 26c worth of work indicating you are ahead of schedule and very efficient
For every R1 spent you have accomplished an extra 26c worth of work indicating you are behind schedule and very inefficient
For every R1 spent you have accomplished an extra 26c worth of work indicating you are under budget and very efficient
For every R1 planned you have accomplished an extra 26c worth of work indicating you are under budget and inefficient
R1 600 000 behind schedule
3. The Cost Performance index at the end of week 5 (rounded to two decimal points) indicates that:
For every R1 planned you have accomplished an extra 26c worth of work indicating you are ahead of schedule and very efficient
For every R1 spent you have accomplished an extra 26c worth of work indicating you are behind schedule and very inefficient
For every R1 spent you have accomplished an extra 26c worth of work indicating you are under budget and very efficient
For every R1 planned you have accomplished an extra 26c worth of work indicating you are under budget and inefficient
4.The Schedule Variance at the end of week 5 (rounded to two decimal points) suggests that:
The project is R1 200 000 over budget
The project is R1 200 000 ahead of schedule
The project is R1 200 000 under budget
The project is R1 200 000 behind schedule
5. The Schedule Performance index at the end of week 5 (rounded to two decimal points) indicates that:

For every R1 planned you have accomplished 87c worth of work indicating you are behind schedule and inefficient
For every R1 spent you have accomplished 87c worth of work indicating you are over budget and inefficient
For every R1 planned you have accomplished 87c worth of work indicating you are ahead of schedule and very efficient
Task | % Complete EV AC PV CV | SV 1 Finished 2000 1500 2000 2 Finished 2400 2000 2400 3 50% 1500 | 800 2000 4 60% 1500 1500 2200 5 25% 400 400 400 Cumulative TotalsStep by Step Solution