Question: Task Duration Dependency T1 8 T2 11 T3 7 T2 T4 5 T3 T5 10 T1, T4 T6 14 T7 8 T6 T8 12 T4,

Task Duration Dependency
T1 8
T2 11
T3 7 T2
T4 5 T3
T5 10 T1, T4
T6 14
T7 8 T6
T8 12 T4, T7

First, Create an activity network and identify the critical path. How long will the project at least take, then Create a corresponding bar (Gantt) chart. Now, At least how many developers will be needed if every task is set to start at the earliest time possible? Answer this question with a feasible staff/task assignment table.