Question: Task Duration Dependency T1 8 T2 11 T3 7 T2 T4 5 T3 T5 10 T1, T4 T6 14 T7 8 T6 T8 12 T4,
| Task | Duration | Dependency |
| T1 | 8 | |
| T2 | 11 | |
| T3 | 7 | T2 |
| T4 | 5 | T3 |
| T5 | 10 | T1, T4 |
| T6 | 14 | |
| T7 | 8 | T6 |
| T8 | 12 | T4, T7 |
First, Create an activity network and identify the critical path. How long will the project at least take, then Create a corresponding bar (Gantt) chart. Now, At least how many developers will be needed if every task is set to start at the earliest time possible? Answer this question with a feasible staff/task assignment table.