Task Immediate predecessor Duration days
a
b a
c a
d b
e b
f c e
g d e
h f g
i h
Do the followings:
a Draw the precedence diagram
b Find the critical path using ESEFLFLS algorithm. Show slack on the diagram
c Determine expected project duration.