Question: Task Immediate Predecessor ( s ) Duration ( days ) A None 2 B None 4 C A 8 D B 1 E C ,
Task Immediate Predecessors Duration days A None B None C A D B E C D F D a Draw the Network diagram and include the Early Starts ES Early Finishes EF Late Starts LS and Late Finishes LF points b What is the expected completion time of this project? points c What is the critical path through this project? points d How much slack is in Activity C What does this mean? points e How much slack is in Activity E points