Question: Task L (1) is missing from this PERT diagram. Which nodes should be connected by Task L? What is the critical path for this project?

Task L (1) is missing from this PERT diagram.Task L (1) is missing from this PERT diagram. Which nodes should be connected by Task L? What is the critical path for this project? How much time will the critical path require?

A (3) E (1) F (1) H (2), I (1 1 2 5 7 8 8 9 10 11 J (1) 16 15 N (1) K(1) 3 6 12 M (1) 14 B (1) O (.5) 17 18 D (1) 4 13