Question: Task Number Predecessors #staff #duration(months) A none 3 2 B none 2 1 C A 3 3 D B 4 2 E C 2 5
| Task Number
| Predecessors
| #staff
| #duration(months)
|
| A | none | 3 | 2 |
| B | none | 2 | 1 |
| C | A | 3 | 3 |
| D | B | 4 | 2 |
| E | C | 2 | 5 |
| F | C, D | 4 | 4 |
| G | F | 2 | 4 |
| H | C,E | 3 | 2 |
| I | H | 2 | 1 |
| J | D, I | 4 | 2 |
a)Draw the schedule path
b)Determine the critical paths and write down the tasks of the critical path