Question: Task Number Predecessors #staff #duration(months) A none 3 2 B none 2 1 C A 3 3 D B 4 2 E C 2 5

Task Number

Predecessors

#staff

#duration(months)

A

none

3

2

B

none

2

1

C

A

3

3

D

B

4

2

E

C

2

5

F

C, D

4

4

G

F

2

4

H

C,E

3

2

I

H

2

1

J

D, I

4

2

a)Draw the schedule path

b)Determine the critical paths and write down the tasks of the critical path