A project has the activity diagram shown below. What is the shortest time the project can be completed?

A project has the activity diagram shown below.

Activity A Dependency n/a n/a A B C D B Duration (Months) 5 2 3 2 4 5 3 1 3 E F G H B C,D E F F G Start Finish E 13 months 15 months 14 months 16 months