Question: Task: Perform following task considering the table given below. 1 ) Create a new project plan and save the file name as yourId . mpp

Task: Perform following task considering the table given below.
1) Create a new project plan and save the file name as yourId.mpp,
Exp: 202134567.mpp (it is must otherwise your assignment will be rejected)
2) Set the 11-05-2024 as starting date of this project.
3) Change the Project Calendar to fulfill the requirement of KSA working environment (5 days and 8:00 AM-5:00PM)
4) Set the date 15-05-2024 as holiday.
5) Enter the title of the project as Learning Management system along with name of project manager and other project related information.
6) Define work in your project plan by configuring the tasks, their duration etc as mentioned in the given table.
7) Set the relationship among the task as mentioned in the table.
8) Define some sample resources of each type (work, material and cost).
9) Configure the material labels and their respective unit cost.
10) Configure the salaries of human resources based on their agreements with
the employer.
Table:\table[[S#,Task,Activity description,Predecessors Tasks,Duration (Days)],[,Initial Phase],[1,A,Fe asibility Study,,4],[2,B,Requirement analysis,A,2],[3,C,Planning,B,5],[4,D,Client accepted the proposal,C,0],[Design and Development Phase],[5,E,Interface de sign,D,4],[6,F,Database de sign,D,3],[7,G,Application Development,\table[[E,],[F]],7],[Implementation Phase],[8,H,ProductTesting,G,2],[9,1,Implementation,H,7]]
 Task: Perform following task considering the table given below. 1) Create

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!