Question: Task Predecessor Duration A 4 3 B C ID A B 2 CD ID E, F 2 5 4 Build an activity-on-node (AON) network diagram

Task Predecessor Duration A 4 3 B C ID A B 2 CD

Task Predecessor Duration A 4 3 B C ID A B 2 CD ID E, F 2 5 4 Build an activity-on-node (AON) network diagram using the list of tasks above. What will be the critical path for this project? Multiple Choice OD-E-G O D-F-G A-B-C-E-G O A-B-C-D-G