Question: TASK PREDECESSOR DURATION (DAYS) A _ 4 B _ 7 C A 6 D A 4 E A 2 F B 5 G B 9

TASK PREDECESSOR DURATION (DAYS)
A _ 4
B _ 7
C A 6
D A 4
E A 2
F B 5
G B 9
H E,F 3
I C,D 6
J G 7
K H,I 4
L J 3
M K,L 5

Identify and calculate the duration of all possible paths on the network diagram and list the critical part