Question: TASK PREDECESSOR DURATION (DAYS) A _ 4 B _ 7 C A 6 D A 4 E A 2 F B 5 G B 9
| TASK | PREDECESSOR | DURATION (DAYS) |
| A | _ | 4 |
| B | _ | 7 |
| C | A | 6 |
| D | A | 4 |
| E | A | 2 |
| F | B | 5 |
| G | B | 9 |
| H | E,F | 3 |
| I | C,D | 6 |
| J | G | 7 |
| K | H,I | 4 |
| L | J | 3 |
| M | K,L | 5 |
Identify and calculate the duration of all possible paths on the network diagram and list the critical part