Question: Task Predecessor Duration A Start 3 B Start 5 C B 8 D A, C 12 E C 7 F D, E 9 Given the
| Task | Predecessor | Duration |
| A | Start | 3 |
| B | Start | 5 |
| C | B | 8 |
| D | A, C | 12 |
| E | C | 7 |
| F | D, E | 9 |
- Given the requisite information above, what is the critical path duration?
b. What are some mechanisms for crashing a project.