Question: Task Predecessor Duration Early StartEarly Finish Late Start Late Finish 8 A B 14 23 A . 8 26 D 6 23 E 32 F

Task Predecessor Duration Early StartEarly Finish Late Start Late Finish 8 A B 14 23 A . 8 26 D 6 23 E 32 F DE 32 38 What is the late finish for activity D in the network shown in the diagram