Question: Task Predecessors Estimated Duration A - 2 B - 1 C B 3 D C 5 E C 4 F D, E 1 G E,

Task

Predecessors

Estimated Duration

A

-

2

B

-

1

C

B

3

D

C

5

E

C

4

F

D, E

1

G

E, F

3

H

F, G

5

I

H

2

  1. Draw a network diagram of the project's activities.
  2. Determine the start and end of the project and the late events
  3. Determine the critical path of project activities.
  4. How will the project be affected if (G) Activity is delayed by two days?