Question: Task Predecessors Estimated Duration A - 2 B - 1 C B 3 D C 5 E C 4 F D, E 1 G E,
| Task | Predecessors | Estimated Duration |
| A | - | 2 |
| B | - | 1 |
| C | B | 3 |
| D | C | 5 |
| E | C | 4 |
| F | D, E | 1 |
| G | E, F | 3 |
| H | F, G | 5 |
| I | H | 2 |
- Draw a network diagram of the project's activities.
- Determine the start and end of the project and the late events
- Determine the critical path of project activities.
- How will the project be affected if (G) Activity is delayed by two days?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
