Question: Task Predecessors Tasks (Dependencies) Time (Weeks A 0 3 B 0 5 C 0 7 D A 7 E B 5 F C 5 G
Task Predecessors Tasks (Dependencies) Time (Weeks A 0 3 B 0 5 C 0 7 D A 7 E B 5 F C 5 G E 4 H F 5 I D 6 J G,H,I 4 Create an AON (Activity on Node) Pert Diagram given the information in the table above. Be sure to identify the slack time for each activity Identify the project's critical path What is the significance of being able to identify critical path? Discuss any three points that will demonstrate the importance of project management to organizations in Jamaica.