Question: TASK SECONDS TASKS THAT MUST PRECEDE A 36 B 20 A C 25 B D 12 B E 30 C F 17 D G 23
| TASK | SECONDS | TASKS THAT MUST PRECEDE |
| A | 36 | |
| B | 20 | A |
| C | 25 | B |
| D | 12 | B |
| E | 30 | C |
| F | 17 | D |
| G | 23 | E, F |
| H | 16 | G |
The workday is 7.7 hours long. Demand for completed product is 630 per day. | ||