Question: TASK SECONDS TASKS THAT MUST PRECEDE A 36 B 20 A C 25 B D 12 B E 30 C F 17 D G 23

TASK SECONDS TASKS THAT MUST PRECEDE
A 36
B 20 A
C 25 B
D 12 B
E 30 C
F 17 D
G 23 E, F
H 16 G
The workday is 7.7 hours long. Demand for completed product is 630 per day.TASK SECONDS TASKS THAT MUST PRECEDE A 36 B 20 A
a. What is the cycle time required to meet the desired output rate. (Specify the time in SECONDS. Enter the numbers only.) Page 2: 44 A 2 b.What is the theoretical number of workstations required to meet the desired output rate? (Enter the numbers only; Round up your answer to the next whole number.) 4 A C. Balance the line using sequential restrictions and the longest-operating-time rule. Which task(s) should be assigned to workstation 111? What is the workstation III idle time? Task(s)____(Use "," to separate the tasks if more than 1 task should be assigned, e.g., B,D) Idle Time_ _____ (enter the numbers only) Idle Time (in seconds) 8 12 Work Station Task 11 B.D 111 IV V GH 5 A/ A/ d. Balance the line using sequential restrictions and the longest-operating-time rule. Which task(s) should be assigned to workstation IV? What is the workstation IV idle time? Task(s). e.g., B,D) (Use "," to separate the tasks if more than 1 task should be assigned, Idle Time (enter the numbers only) A A

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!