Question: TASK SECONDS TASKS THAT MUST PRECEDE A 2 5 B 2 0 A C 1 6 B D 3 5 B E 2 7 C

TASK SECONDS TASKS THAT MUST PRECEDE
A 25
B 20 A
C 16 B
D 35 B
E 27 C
F 15 D
G 10 E, F
H 35 G
The workday is 8.75 hours long. The demand for completed product is 700 per day.
Find the cycle time required to meet the desired output rate.
Note: Round your answer to 1 decimal place.
What is the theoretical number of workstations required to meet the desired output rate?
Note: Round up your answer to the next whole number.
Balance the line using sequential restrictions and the longest-operating-time rule. Determine the task under each workstation and the idle time for each such task.
Note: Leave no cells blank - be certain to enter "0" wherever required. Round your answers to 1 decimal place.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!