Question: Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows: Activity Time (in hours) Immediate Predecessor(s)

Task time estimates for the modification of an assembly line at Jim Goodale's Carbondale, Illinois, factory are as follows:

Activity

Time

(in hours)

Immediate Predecessor(s)

A

6.0

-

B

7.0

-

C

5.0

A

D

6.0

B, C

E

4.5

B, C

F

8.0

D

G

4.0

E, F

This exercise contains only parts d, b, and c.

d) Using the line drawing tool five times, draw a Gantt chart for activities C through G of the project based on the early times.

Carefully follow the instructions above, and only draw the required objects.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!