Question: task variable cost added at step yield 1 $15.00 96.0% 2 $10.00 92.0% 3 $7.00 94.0% 1 a) What is the yield for this process

task variable cost added at step yield
1 $15.00 96.0%
2 $10.00 92.0%
3 $7.00 94.0%

1 a) What is the yield for this process rounded to 1 decimal point?

b)What would the variable cost of a good unit be if yields at each step were 100%?