Question: Task Work Task Time Task Predecessor(s) (seconds) 140 B 120 JA 240 1120 480 C D 400 A G 380 E,F Answer the questions based

Task Work Task Time Task Predecessor(s) (seconds) 140 B 120 JA 240 1120 480 C D 400 A G 380 E,F Answer the questions based on a 50 demand per day and an 7 hours of working hours Minimum number of work stations to balance this process = 2 Minimum number of work stations to balance this process = 3 Minimum number of work stations to balance this process = 4 Minimum number of work stations to balance this process = 5