Question: WorkLask Task Task Time Predecessor(s) (seconds 140 B 120 A C 240 B D 120 E 480 CD F 400 380 EF G Answer the

WorkLask Task Task Time Predecessor(s) (seconds
WorkLask Task Task Time Predecessor(s) (seconds 140 B 120 A C 240 B D 120 E 480 CD F 400 380 EF G Answer the questions based on a 50 demand per day and an 7 hours of working hours O Efficiency 73% 72% Efficiency O Efficiency 72.9% O Efficiency 74,5%