Question: TaskB 2 weeks Task D 1 week Task A 4 weeks Task F 8 weeks Task C 5 weeks Task E 8 weeks b. Calculate

TaskB 2 weeks Task D 1 week Task A 4 weeks Task FTaskB 2 weeks Task D 1 week Task A 4 weeks Task F

TaskB 2 weeks Task D 1 week Task A 4 weeks Task F 8 weeks Task C 5 weeks Task E 8 weeks b. Calculate slack for every project activity. (Leave no cells blank - be certain to enter "O" wherever required.) Task Latest Completion Latest Start Immediate Successors None Slack F E F D F C D, E B D A B, C