Question: TASKS Predecessor Task Time A Warm tortilla -none 20 sec B Rice -A 10 sec C Beans -B 10 sec D Meat -B 10 sec
| TASKS |
| Predecessor | Task Time |
| A | Warm tortilla | -none | 20 sec |
| B | Rice | -A | 10 sec |
| C | Beans | -B | 10 sec |
| D | Meat | -B | 10 sec |
| E | Salsa | -C, D | 10 sec |
| F | Cheese | -E | 5 sec |
| G | Sour Cream | -E | 10 sec |
| H | Lettuce | -E | 10 sec |
| I | Wrap | -F, G, H | 15 sec |
| J | Bag | -I | 5 sec |
| K | Checkout/pay | -J | 25 sec |
- Achieving the above cycle time and output, what is the theoretical number of workstations?
- Assign tasks to workstations:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts