In a MRP problem, A is a MPS item. Every A requires 3 B's and 2 C's. Every B requires 5 C's. All lead times are one period. Initial inventory values for all items are 0. Use lot-for-lot method for order quantities for all items. If gross requirement for A is 400 in period 10, what will be the planned order release for C in perlod 8?
Multiple Choice
1,200
800
6,000
1,600
6,800