Question: TB MC Qu. 09-84 In an MRP problem, A is an MPS... In an MRP problem. A is an MPS item. Every A requires 2

TB MC Qu. 09-84 In an MRP problem, A is an MPS...
TB MC Qu. 09-84 In an MRP problem, A is an MPS... In an MRP problem. A is an MPS item. Every A requires 2 B's and 3 C's. Every B requires 5 C's. All lead times are two periods. Initial Inventory values for Als 100. Bis 200 and C is o. Use lot-for-lot method for order quantities for all items. If gross requirement for Ais 800 in period 9 what will be the planned order release for Bin period 5? Multiple Choice 800 o 1,600 O 1.200 700 1.400